The Catcher FPSO sailed away on 26th August from Singapore. It will take around 45 days to reach the UK North Sea, following which it will be connected and commissioned, a process expected to take 60-65 days with first oil targeting December.
The project is on schedule and c.30% below budget. Development drilling results have been promising with 30% more net pay and 40% better well deliverability. Expected plateau will now increase by 20% to 60mboepd with a potential for reserves upgrade from the 96mboe 2P at sanction.
The Catcher field partners are: Premier 50% operator, Cairn Energy 20%, MOL 20% and Dyas 10%.
Monday 28 August 2017
Sail-away to Catcher