The PJM RRI was a one-time, expedited process launched by PJM to address near-term concerns about resource adequacy due to factors like significant load growth (e.g., from data centers), accelerated generator retirements, and the time it takes for new resources to complete the standard interconnection process.
Here are the key points about the PJM RRI:
- Purpose: To quickly bring "shovel-ready" generation resources online that can most effectively contribute to grid reliability in the PJM region.
- Mechanism: It allowed a limited number of new or upgraded generation projects (up to 51 were ultimately selected) to bypass the standard queue and join Transition Cycle #2 (TC2) of PJM's reformed interconnection process. This accelerated the study and approval timeline.
- Project Selection: Projects were selected based on a weighted scoring formula that primarily considered:
- Market Impact Criteria (e.g., Unforced Capacity (UCAP) and Effective Load-Carrying Capability (ELCC), which measure reliability contribution).
- Commercial Operation Date Viability Criteria (e.g., the planned in-service date and the project's readiness, such as permitting, equipment, and financing).
Result: The initiative successfully selected a mix of projects, including uprates to existing natural gas and nuclear facilities, as well as new battery storage and gas construction, with the goal of adding significant reliable capacity to the grid.
In short, the PJM RRI was a temporary, emergency measure to boost the grid's resource capacity and maintain reliability in the face of rapidly changing electricity supply and demand dynamics.